Window installation on Phase 1 is officially completed and Phase 2 is now being closed in. The drywall has now commenced on the lower floors of Phase 1 and will continue for the next several months. Masonry work continues and at this time, the brick is installed on 3 sides of Phase 1. Mechanical, ventilation and electrical work progresses in both buildings.