We have achieved completion of the concrete structure and poured the concrete roof slab of Building #2 on January 29, 2020. There are some further areas to pour in concrete that will occupy the next few weeks but we are removing the crane from the site by mid-February. This date also coincides with the first supply and installation of windows which will start to enclose the structure. Brick work on the exterior is already underway and certainly the exterior façade is starting to take shape. We have been fortunate this winter with milder temperatures and very few lost days which is allowing construction to progress extremely well.